Watershed scale analysis · Midwest

Scaling observed bioreactor performance to watershed decisions

Connect field monitoring with watershed modeling to examine where treatment could be placed and how different adoption scenarios may affect downstream nutrient loads.

Approach
Identify nutrient pressures, evaluate bioreactor placement and treatment scenarios, and compare expected benefits with implementation costs.
Field basis
Monitoring locations at Geneseo, Walnut, Galva, Rock Creek, Springfield, and Heyworth provide site context for this scale up work.
Monitoring · Watershed modeling · BMP scenarios · Techno-economics

Loading site map…

Explore six bioreactor monitoring locations
Bioreactor based infrastructure at these sites was installed and monitored over the 2017–2026 period; some newer sites have been monitored since 2022. Select a marker to see its location and explore how each site contributes a distinct record over time. Markers may indicate the locality rather than the exact instrument position.
Regional map showing mapped tile-drained areas in green and field water quality observation sites in pink
Regional scale up analysis
Green shows mapped tile-drained areas; pink points mark field-scale water quality observation sites monitored for at least one full year. The map supports assessment of the techno-economic viability of a two-stage treatment train for nutrient reduction across heavily drained Midwestern landscapes.
Map of the Salt Creek catchment near Elberon, Iowa, with tiled areas in green and untiled areas in purple
Salt Creek catchment near Elberon, Iowa
Tiled (green) and untiled (purple) areas, from Figure 1 of the team presentation. View full size ↗
Agricultural drainage · Iowa · team study

Agricultural drainage and streamflow

Examined how tile drainage and precipitation relate to streamflow and flooding patterns in the Salt Creek catchment near Elberon, Iowa.

Approach
Developed a simple watershed water balance model and compared tile drainage scenarios with observed streamflow and precipitation to examine changes in flow patterns over time.
Finding
In the study analysis, tile drainage appeared to affect baseflow seasonality, while precipitation had a greater influence on flow magnitude. The simple model did not explain annual flow partitioning fully.
Team
Eby Lukose, Haribansha Timalsina, and Rahmat Ekanovin.
Water balance · Tile drainage · Streamflow · Flood patterns
Explore the presentation ↗
Woodchip bioreactor installation at the Springfield, Illinois field site
Springfield, Illinois · field installation
Field monitoring · Illinois

Tracking nutrient removal in agricultural drainage

Monitored flow and nitrate concentrations in a field-scale woodchip bioreactor across changing drainage conditions.

My contribution
Field sampling, flow analysis, data checks, modeling, and interpretation.
Evidence
The field study reported a 58% average nitrate concentration reduction through the bioreactor.
Monitoring · Water quality · Drainage
Read the field study ↗
Hari beside paired woodchip and phosphorus treatment columns in the laboratory
Illinois water quality lab · treatment columns
Nutrient treatment · Lab and pilot

Pairing woodchips with phosphorus filters

Tested how denitrifying woodchips and bottom ash pellets can be paired to address both nitrogen and phosphorus in drainage water.

My contribution
Designed treatment configurations, analyzed nutrient removal, and assessed material performance and costs.
Finding
Woodchips followed by bottom ash pellets performed strongly across the lab treatment configurations.
Bioreactors · Sorption media · Techno-economics
Read the materials study ↗
Schematic from the 2026 paper showing field inputs, the neural network, physical nitrate-removal constraints, and the combined training loss
PINN framework schematic · Fig. 2 in Timalsina et al. (2026) · View full size ↗
Model development · Illinois

Predicting nitrate removal with a physics-informed model

Combined field observations and process constraints to estimate nitrate removal in woodchip bioreactors, then compared the model with other approaches.

My contribution
Prepared field data, trained models, compared predictions, and evaluated transfer across sites.
Result
The model substantially outperformed a conventional biokinetic model while matching a purely data-driven neural network’s accuracy. It retained physical consistency and adapted to a new site through partial transfer learning.
Python · Machine learning · Process modeling
Read the modeling paper ↗
Hari documenting a water supply site during an engineering survey in Sindhuli, Nepal
Sindhuli, Nepal · engineering survey
Water infrastructure · Nepal

Surveying rural water supply sites

Documented water infrastructure and site conditions to inform planning and hydraulic assessment in rural communities.

My contribution
Field surveys, water supply network layout planning and design, cost estimation, and report preparation.
Output
Water supply network layout, cost estimate, and engineering report informed by site measurements.
Field survey · Water supply · Hydraulics
See the Field Gallery ↗
Lachlan catchment · interactive map
Pan and zoom to explore the NSW catchment boundary ↗. This is an administrative boundary and may differ from the hydrological study area. Explore the Bureau of Meteorology catchment view ↗
River basin management · Australia · team project, 2025

Balancing reservoir operations and environmental flows

Analyzed flow changes in the Lachlan River after Wyangala Dam’s enlargement and used a GAMS reservoir model to compare hydropower and environmental flow targets.

My contribution
Analyzed hydropower dam operations and ecological flow tradeoffs using a GAMS river basin optimization model, integrating Indicators of Hydrologic Alteration (IHA) for environmental flow targets; co-wrote the results and produced the river network figure.
Finding
Modeled wet and normal initial storage met selected monthly flow targets; the dry scenario met them only in August and September.
Scope
A 2015–2016 water-year model with estimated monthly demands. The report notes missing precipitation inputs as a limitation.
IHA · GAMS · Reservoir storage · Environmental flows
Explore the river network ↗

Also working across stormwater, watershed modeling, and BMP implementation ↗

Communicating project outcomes

Browse selected slides, analyses, and report pages from these projects.

Research design · University of Illinois

Decentralized nature based water treatment

Designing a treatment train that pairs iron amended biosand and woodchips to study nutrients, microbes, and metals in water used for food production.

Presented by Haribansha Timalsina, 2026.